Collado Villalba March 29, 2007 .
D. Thomas Alberich (IU), [on the 10 th monthly report works] is business as usual, nothing happens, when in fact there has been cracks, evictions, floods , etc, the report seems a joke and an embarrassment . Bring a report with four photos and four figures that is not a report of the project management.
D. Alberto Sánchez (ADEI), asks the following questions:
- Are you going to officially inform the work delay Honorio Lozano-Battle of Bailen?
- Have you checked and occupation of the plot assigned to the UTE Cover-Ortiz?, Is it going to take action?
D. Joseph A. Gómez Sierra (PSOE), tomorrow will be a Commission reports which will be officially informed of the delay which will then come to the House as contracting authority. On the occupation of the plot of ITV, as set out in clause 35 of the sheets looked 20,000 m2. The contractor is responsible for processing the waste. He has a technical report that says the main bunch occupies 16,350 m, and the other just spend lots of 20,000, the occupancy will fade over the next 6 months . [remember that this statement took place in March-2007] D. Alberto Sánchez (ADEI), who signed the report of Monte Cover?
D. Joseph A. Gómez Sierra (PSOE), D. Polin Juan Guillen.
D. Alberto Sánchez (ADEI) the content of the report is clearly uncertain is disastrous meters that are passed in the area, do not understand how the Environment has not gone already, not understand how they are not falling of shame in relation to these works , we will have a full to talk at length about the work. The initial fence was on the farm was exceeded by far have doubled meters, is willing to accompany him on the measurements, this permissiveness with neighbors is not taken. (...) On architectural barriers are now raising Battle of Bailen again to lower the zebra crossings, not know if the delay is because they are very bad doing the work.
D. Thomas Alberich (IU), asks the following questions:
- How many cracks and "cracks" have appeared on buildings Honorio Lozano Street, next to the tunnel current work-Parking?
- Do you have a deadline for the works? Is it going to impose any penalty on the company by delays ? Is it going to impose any sanction for non compliance with the promise maintenance of traffic during construction transverse?
- The newly opened Battle of Bailen street not compliance with local laws governing non-physical barriers and creating the obligation to provide accessibility to disabled people "are going to work to remedy these defects? How is it possible that this street has been opened completely remodeled and both will cost us all neighbors without forced the company to remove architectural barriers denounced by some neighbors in a while?
D. Joseph A. Gómez Sierra (PSOE) [not answer any of these issues]
D. Thomas Alberich (UI), does not answer the questions you have raised and the council has answered things we have not asked. About cracks or fissures regrets not agree, shows photos, says there are 9 mm. Considered scandalous what is brought to the Information Commission tomorrow, there is a project of additional works, consider outrageous prices, take him to a full ordinary to extraordinary. This is a scandal. seems that the goal is that nobody learns . Considers that the extension of the work comprises things already planned. We will look in detail this project, and if necessary, will take the courts. Some neighbors Villalba arise if the governing PSOE, PSOE Cover or whoever. No specifications have been met or will meet deadlines is a serious issue . Yesterday started to remove the differences of Battle of Bailen, they gave the question a week ago. Architectural barriers in all steps zebras get the same level, so they have to fix it and had to have corrected earlier.
Ms. Carmen Rodriguez (PP), asks the following questions:
- How many square meters of land municipal currently holds the deposit of inert in the area of \u200b\u200bITV?
- How many trees are gone under the waste?
- Does the deposit all authorizations, including the crushing of waste, the Ministry of Environment of the Autonomous Community of Madrid?
- Who is responsible for requiring the licensee of the work the perfect maintenance of public roads by passing trucks that work?
- Has there been any measurement of noise emissions and dust pollution in residential areas of the environment?
- As previously reported the important delay in funding [sic] of the work, Will we have to suffer the residents throughout the summer and noise pollution?
- What solutions do they propose to neighbors who pay our taxes strictly to enjoy our homes?
D. Joseph A. Gómez Sierra (PSOE), in terms of solutions is referred to the homes affected by noise and dust, no one is able to execute a project of this magnitude without noise and inconvenience. To be in area near the landfill space, they must deal with the consequences of a parallel execution of the work, you can not do otherwise, but for the end zone for the inconvenience rather than for the others. As the occupancy rate is hovering the 20,000 m2, there is plot to continue placing. Everyone knew the circumstances in the statement of the plots, not aware that they have disappeared trees, although there is a risk that any disappears, this area is the site where the General Plan, not a park or a protected area . On permits, there is an inspection report on August 1 of the Community of Madrid, Department of Environmental Quality, which has been answered a month later with a report of techniques, the Community of Madrid has understood that it is an activity as part of another core activity, you can transfer the file. On cleaning , the department and the Department of Environment have demanded that they do have a sweeper in the area. Besides the streets needed to perform the work will to replace them again.
Ms. Carmen Rodriguez (PP) in the area of \u200b\u200bthe ITV is being crushed breach current regulations, the area falls on a rain of dust until 9 pm. Do not tell me it's a matter of the work. If you have more occupied meters, pay rent, we have given them an important part of local heritage, if they need more pay meters which . I asked if they have a permit and has not referred in his question to any record because the record is not an authorization, insists that no watering necessary to make a crushing. many trees have disappeared, we are not ciegos. El Área de Medio Ambiente pone multas, pero si es Cover, no . Han hecho baches , se acumulan piedras y barro en las entradas de las urbanizaciones. La barredora fantasma es invisible, le parece indignante, es una vergüenza pública que los vecinos no tenemos porqué soportar. Tienen que mantener las vías en perfectas condiciones, no tenemos por qué sufrir el polvo, el ruido, etc. Deberían tomárselo en serio, no entiende porqué teniendo ustedes los medios para obligarles a cumplir un contrato tan beneficioso para ellos no los utilizan.
D. José A. Gómez Sierra (PSOE), a Cover file has been opened.
--- Previous chapters:
- Full Municipal Collado Villalba (I)
- Full Municipal Collado Villalba (II)
- Full Municipal Collado Villalba (III)
- Full Municipal Collado Villalba (IV)
- Full Municipal Collado Villalba (V) ---